A Graph Of Ease

Irving Underhill, in 1914, caught the Equitable Building (the Equitable Life Assurance Company Building, not the Equitable Trust Company Building) with the frame complete and the facade maybe 80 percent done:

One of the advances in construction that was enabled by the switch to skeleton framing at the end of the nineteenth century was the ability to start building the exterior walls at any floor. If the wall is supported at each floor, then each piece of wall from one floor to the next is independent of the others, and therefore the pieces can be built in any order. In general, the order that contractors chose was from the second floor up, leaving the first floor open for materials traffic but otherwise following simple bottom-to-top sequencing.

So, why the gap from the 25th floor to the 30th? Here’s the completed building in July 1915:

If you look closely, you’ll see that the upper patch of complete facade starts at the lower of the two watertables at the 30th and 31st floors. Something you can’t see in these photos is that most of the facade is brick, and the ornament is terra cotta. The facade from the 8th floor to the 30 is very plain, with the ornament clustered above and below. (The lower ornament is readily visible to passers-by; the upper ornament is readily visible to people in other tall buildings, people looking from a distance, and pigeons.)

Based solely on these two photos, I’ll take a guess: the facade at the upper floors was going to take a long time to build, so it was started after the lower-floor facade was built up as far as the typical floors starting at the 8th. The lower band of construction moved faster than the upper because it was simpler to build, but had more area to cover.